The Los Altos Main Library is set to undergo a massive interior renovation next year and the city’s Library Commission met Aug. 6 to discuss the library’s closure and mitigation plans during the construction.

The remodel plan was established during a January 2024 meeting during which the commission’s ad-hoc subcommittee laid out the concept of the roughly $9 million project that would uplift the aging library that was initially constructed in 1964 and hasn’t been updated since 1990. The staff report estimates that the library will be closed for upwards of 18 months.

During the closure, which will specifically affect community members in North Los Altos who frequent the main branch, the plan is to leverage the Woodland Branch in South Los Altos as well as the Los Altos Community Center, just east of the main library.

“At its core, the strategy relies extensively on our existing public infrastructure,” staff wrote in a report to the commission.

Staff shared mitigation tactics during the closure, including preparing the Woodland branch for increased hours and staffing; activating the civic center to relocate youth and senior programs to the community center and local parks; partnering with Santa Clara County Library District to position around the clock automated holds lockers at high-traffic hubs; and safeguarding specialized services like passport services to neighboring branches and pivoting Friends of the Library toward continuing operations.

Staff highlighted some concerns, including ensuring that the community spaces, early literacy programs and tech help that the seniors and youth of Los Altos rely on the library for remain available in some capacity; the geographical equity with all North Los Altos impacted by the closure; traffic and parking issues around Woodland branch; and staffing and operational considerations.

Staff presented three separate scenarios to the commission. Scenario one is the lowest-cost option where they would leverage existing infrastructure only. The second scenario, a medium-cost option, would be an enhanced plan that incorporates a decentralized pop-up and mobile network like 24/7 smart hold lockers, dedicated BookMobile routes to create “Los Altos Library Days,” and mini-library browsing kiosks. The third and highest-cost scenario would be to lease a temporary commercial storefront in downtown Los Altos or place a modular library structure on civic land to maintain a dedicated footprint.

Ultimately, staff recommended a hybrid framework combining scenarios one and two “to achieve the highest level of service continuity while remaining strictly protective of city fiscal resources.”

“By expanding the hours of the Woodland branch, using the Los Altos Community Center for youth and senior programming, installing a 24/7 automated holds locker and seamlessly shifting passport and (Friends of the Library) frameworks, Los Altos can successfully mitigate the renovation,” staff said in the report. “This approach ensures our community remains deeply connected, literate, and engaged while preparing for a beautifully modernized Main Library.”

Staff said that community buy-in is key so informing residents in a timely fashion is essential.

“A robust communication campaign must launch in late fall 2026,” staff said in the report, “aligning with the Library Commission’s current work plan goal to educate the public on construction.”

Phase one of the communication plan would be to raise awareness in early 2027 by launching “an aggressive outreach campaign utilizing the Los Altos Town Crier, city newsletters and physical banners. The core message must be: ‘The Library building is closing for upgrades, but Los Altos Library services are simply moving.’”

The second phase in the spring of 2027 is system preparation and automatically transitioning the default holds-pickup location for all 94022 and 94024 zip code accounts to the Woodland branch or the newly-installed smart lockers.

And the third phase, launch and maintenance, will take place in early 2028, deploying signage at the dark Main Library site directing foot traffic to the Community Center and Woodland, as well as providing regular construction milestone updates via social media to maintain community excitement for the grand reopening.